3D Progress
Element Registry Back
View
X-Ref
Flight
Progress
0
Elements
0
Active
0
Complete
Status
Not started
In progress (% built)
Complete
TBM tunnels (below ground)
Bored — rings placed
Not bored
CREG cutterhead · shield
Ø9.3 m lining ~16 m deep; tilt low to look under the ground
Viaduct spans (LG progress)
Erected — always shown
Cast — awaiting erection
Partially cast
Not cast
The three planned states need the Viaduct tab; click a span for its dates
Road works
Asphalt build-up (4 courses)
wearing · base · road base · sub-base — each solidifies with its own reported activity
Interlock paving
Interlock — blue paving (in-road)
Footpath — interlock blocks on bedding
Kerbs
Markings
Ghost = designed, no approved report
Solid = reported (opacity = % complete)
Utility works (proposed)
Storm water
Sewerage (foul)
Irrigation
Potable water
DEWA 132/400kV
DEWA LV/11/33kV
Gas · Cooling
Street-light poles (lamp glows)
Du ITS · Etisalat · RTA duct
Traffic signals (poles, MH, ducts)
Tubes at real Ø from drawings/labels; click for spec
X-ray dims road surfaces to reveal them
Landscaping works
Station hardscape / paving
Softscape stays in RUL Works (no drawing yet)
No layers are switched on, so there is nothing to explain yet. Turn on a layer from the top bar or the left toolbar and its key appears here.
✕
—
—
Overall 0%
✕
—
—